HS Group continues to provide direct technical supervision for the reconstruction of the strategic water tank in Khormaksar District, Aden, one of the key water infrastructure projects supporting the city’s water security.
Implemented by Dome International, the project has achieved significant construction progress, with 100% of the tank roof installation completed and two of the six steel wall layers successfully installed.
The project utilizes the Hydraulic Jacking Method, an advanced construction technique in which the roof and upper structural sections are assembled first before the entire structure is hydraulically lifted to allow installation of the remaining lower wall layers.
Preparations are currently underway for the lifting operation, which will enable the installation of the remaining four steel wall layers in accordance with the approved project schedule.
The project is being implemented in collaboration with the Social Fund for Development (SFD), with support from KfW Development Bank and the Government of the Netherlands. HS Group’s technical supervision contributes to quality assurance, construction precision, and the delivery of sustainable water infrastructure for the local community.