Environmental strategy and costal management plan for Aden governorate, revising and updating the master plan of Aden city.


Research: Environmental Strategy and Costal Management Plan.Location: Aden, Yemen.

Client: Port Cities Development Program (PCDP) IDA project

Address:
Port Cities Development Program (PCDP) Aden, Khormakser
Tel:  + 967 2 239-171/2
Fax: + 967 2 239-165

Start Date: July 2004Completion Date: 2006

Duration of Assignment: 2 years

Approx. Value: $1,198,000

Total No. of staff-months: 70

Associated Consultants (AC): HARLCROW Company, UK

No. of staff-months by AC: 30

Involved seniors:
Project Director: John Smith
Team Leader: Steve Crowherst
Local Coordinator: Hani Sahooly

Project’s Brief

  • To include a modern concrete building that will consist of thirteen floors, three to be commercial mall and nine administrative floors to include open plan offices and all facilities for a modern office building.
  • Highly advanced architectural finishing, the external cladding to be mostly Aluminum sheets, glass and local off white stones
  • Approximate total built area of 12,000 m2 including the main courtyard, fix structures and circulation elements.
  • Complete MEP systems and works including sound system, CCTV, firefighting, data system, etc.
  • The landscape designs to include hard and soft landscape, irrigation systems and external lighting

 

Landscape and Fencing:

  • Green areas and soft landscape.
  • Pavement and hard landscape.
  • External lighting system.

 

Scope of Service
Design consultancy services include the following:

  • Prepare technical report including area and space requirements, site analysis and concept design etc.
  • Prepare conceptual architectural designs.
  • Prepare preliminary architectural designs.
  • Prepare (3D) digital model using 3D MAX software.
  • Prepare model scale 1:200 using cardboard and wood.

 

 

 

 

 

 

 

 

 

 